Tooling
Cycle:
If the customer supply the 3D data,the normal tooling cycle is 28
days,that is:
Product Design 4 days
Tooling Structure Design 4 days
CNC Processing 4 days
EDM Processing 5 days
Machine Processing 5 days
Polishing and Precision Processing 4 days
Assembly and Debugging 2 days Sample
Recycle
After 3 days for the tooling test,we offer the T1 sample
Production
Recycle
After the sample are confirmed ,we use 5-7 days to prepare the material,then
begin the mass production,the daily output is 2500-3000 pcs for
one item bar phone whose tooling is only one cave for one part,and
1500-2500pcs for one item flip phone.

Currently,the month output
is over 90 sets for the dummy phone tooling ,it is equal 20 styles
of dummy phone.There are 8 lines in our assembly workshop and there
are 36 seats in per line.If all the lines are working ,the month
output will be over 500K pcs.
|